What a Garage Conversion ADU in Melissa, TX Actually Costs and Involves
A Garage Conversion ADU in Melissa typically runs $45,000 to $130,000 and takes 8 to 16 weeks from permit to final inspection. You’re turning an existing attached or detached garage into a legal, rentable or family-ready living unit with its own sleeping area, kitchenette, and bathroom, not just finishing out a room. Most of the cost sits in plumbing, electrical, and the new slab or subfloor transition at the former garage door opening. Call (888) 426-8078 for a free on-site estimate.
How We Run a Garage Conversion ADU, Stage by Stage
Every garage conversion follows the same general track, but the order matters because HVAC, plumbing, and framing all compete for the same cavity space inside a garage shell. Here’s what our technicians with up to 12 years of experience work through, and where you’ll make decisions.
- Stage 1 – Site review and design, weeks 1 to 2. We measure the existing slab, check ceiling height against the minimum ceiling requirement for a habitable room, and confirm whether the garage is attached or detached. At this point you decide the floor plan: studio, one-bedroom, or one-bedroom plus kitchenette. That decision drives everything downstream, including where the bathroom lands relative to the existing sewer line.
- Stage 2 – Permitting and utility disconnect, weeks 2 to 4. Melissa’s permitting office reviews the plans, and the timeline depends on how complete the drawings are. You decide the fixture locations here, because moving a drain after the slab is cut is where budgets blow up. We pull the permit and coordinate inspection scheduling.
- Stage 3 – Demolition, trenching, and rough-in, weeks 4 to 7. Out come the door and opener, the old drywall, and any storage shelving. Then we cut the slab to trench plumbing to the new bathroom and kitchenette, run electrical circuits, and frame interior walls. Inspectors review the rough framing, plumbing, and electrical before anything gets covered. This is the noisiest, dustiest stretch.
- Stage 4 – Insulation, drywall, mechanical, weeks 7 to 11. We insulate the walls and ceiling to bring the garage up to the thermal performance of the rest of the house, install HVAC, hang and finish drywall, then set cabinets, flooring, fixtures, and finishes. You decide material grades in this window if you haven’t already.
- Stage 5 – Final inspection and punch list, weeks 11 to 16. The city signs off on the final inspection, we walk the unit with you, and you get the keys to a finished ADU under our 730-Day Done Right Promise. Any correction we owe, we handle.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Choices You’ll Actually Make on a Garage Conversion ADU
A garage is a shell with a concrete slab and a big hole where the door was. The conversion is mostly about closing that shell up correctly and choosing finishes that hold up in a small footprint.
- Floor system: A floating subfloor over the existing slab keeps the finished floor at a livable height and manages minor slab imperfections. A direct-glue or self-leveling approach costs less and gains a few inches of ceiling, but it’s unforgiving of slab cracks. For garages in older Melissa builds where the slab has settled, we usually recommend the floating system with rigid foam underlayment.
- Former door opening: You can frame in a wall with a new window and walk door, or install a large sliding glass or French door for light. A framed wall with an insulated window is the cheaper and better-insulated choice; a glazed opening looks great but adds cost and solar heat gain you have to manage with shading or Low-E glass.
- Kitchenette: A compact sink, under-counter fridge, and two-burner cooktop is the practical minimum for a legal ADU kitchenette. Full-size appliances cost more and eat floor space. KraftMaid and similar cabinetry lines work well in these small runs because they offer narrow widths and shallow depths that standard stock doesn’t.
- HVAC: A mini-split system handles a single-zone ADU efficiently and avoids running ductwork through a low attic. An extension of the home’s central system can work if the garage is attached and the existing unit has capacity, but that’s a load calculation, not a guess.
- Structural: Detached garages often need a new structural beam across the former door span once you remove the garage door header. That’s a design and engineering item we identify early, not mid-build.
What a Garage Conversion ADU Costs in Melissa, TX

Plan on $45,000 to $130,000 for a garage conversion in Melissa. The range is wide because the low end is a studio with a kitchenette and the high end is a full one-bedroom with a full kitchen and premium finishes.
| Line item | Typical Melissa range |
|---|---|
| Permitting and design | $2,000 – $7,000 |
| Demolition, framing, slab work | $6,000 – $18,000 |
| Plumbing rough-in and fixtures | $5,000 – $15,000 |
| Electrical and panel upgrade | $3,500 – $12,000 |
| HVAC (mini-split or extension) | $4,000 – $11,000 |
| Insulation, drywall, paint | $5,000 – $14,000 |
| Kitchenette and bathroom finishes | $8,000 – $28,000 |
| Flooring and trim | $4,000 – $14,000 |
| Contingency (10 – 15%) | $4,000 – $11,000 |
Four variables decide where you land. Size and floor plan come first: a one-bedroom with a full bath and full kitchen runs to the top of the range, a studio closer to the bottom. Existing condition is second; a clean, level slab saves money, and a settled or cracked slab adds repair before you build. Third is the plumbing and electrical distance from the main house; dragging a sewer line 40 feet to a detached garage is real trenching cost. Fourth is finish grade; mid-grade fixtures and standard cabinets sit well under custom. Permitting scope is fifth: adding a bathroom where none existed triggers more inspection stages.
Our written estimates are line-item and fixed. The number you see is the number you pay, with no change orders unless you change the scope. The estimate covers permits pulled, materials, labor, and final inspection. It typically excludes landscaping restoration around a detached garage, specialty appliance purchases beyond the kitchenette allowance, and any structural engineering report if one is required for a detached conversion.
See the difference
Before
After
Before
After
Before
AfterWhat Melissa Homes Specifically Do to This Job
Melissa’s housing stock changes the math on a garage conversion. Most of the city is newly built single-family homes in master-planned subdivisions, so we’re working on two- to twenty-year-old garages with builder-grade framing, standard 8-foot ceilings, and often a builder-installed opener and flimsy utility door. That’s good news for framing; the walls are true and the slab is stable in most cases. The catch is the blackland prairie clay under this area. It swells and shrinks with our wet-spring, dry-summer pattern, and that movement shows up as slab cracks and door-opening skew in conversions. We check the slab for movement before we commit to a floor system, because a self-leveling pour over a moving slab cracks again within a season. For attached garages we watch the transition at the former door opening, where foundation movement can show as a gap or a sticking door; for detached garages we check separately whether that slab has heaved at the corners.
The other local wrinkle is permitting. Melissa’s building department has been reviewing a lot of new-construction submittals as subdivisions go up, and the codes here differ in places from McKinney’s or Anna’s. Get the drawings complete and correct on the first pass and the review moves faster. We account for that in the schedule. Homeowners across the Melissa and Melissa service area in ZIP 75454 use a garage conversion to add rental income or a spot for aging parents, and the ADU design work that supports it sits inside our broader Home Additions & ADU service. If the conversion is part of a full Home Additions & ADU in Melissa plan, we scope it together so you’re not paying twice for the same permit. Homeowners often pair this with Cabinets & Countertops in Melissa for a proper kitchenette, and with Backsplash, Tile & Flooring in Melissa for the bath and entry.
Serving Melissa, TX – Our Local Coverage Area
We serve Melissa and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked Questions

A Garage Conversion ADU in Melissa takes 8 to 16 weeks from permit issuance to final inspection. The permit review itself adds 2 to 4 weeks depending on how complete the drawings are; build time after that is roughly 6 to 12 weeks. Call (888) 426-8078 for a schedule that fits your project.
Yes. Any garage conversion that creates a habitable living space requires a building permit, and typically separate electrical, plumbing, and mechanical permits as well. We pull the permits and pass the inspections. Call (888) 426-8078 if you want to know what your specific project triggers.
Sometimes, but it depends on where the bathroom goes. If you can place the bathroom within about 10 feet of an existing sewer line and the garage is attached, the plumbing run stays short and cheap. Detached garages almost always need a new line trenched in, and removing a garage door header usually means adding a structural beam. We assess both in the first two weeks. Call (888) 426-8078 for a site review.
A Garage Conversion ADU in Melissa costs $45,000 to $130,000, depending on floor plan, finish grade, and how far plumbing and electrical have to run. A studio with a kitchenette sits near the low end; a full one-bedroom with a full kitchen and premium finishes reaches the top. Call (888) 426-8078 for a fixed line-item estimate at no cost.
Every conversion we build is backed by our 730-Day Done Right Promise, which covers our workmanship for two full years. If something we installed fails or isn’t right, we make it right. Systems and appliances carry their own manufacturer warranties on top of that. Call (888) 426-8078 to go over the details.
Get Your Free Garage Conversion ADU Estimate
If you’re thinking about a garage conversion ADU in Melissa, the next step is a free on-site estimate. A live person answers the phone 24/7, and we’ll schedule a visit where we measure the garage, check the slab, confirm utility runs, and hand you a written line-item quote – permits, labor, materials, and a fixed price with no surprises. Calls are answered by real people around the clock, and our technicians are background-checked and arrive in uniform. Call (888) 426-8078 to schedule yours.