Junior ADU & Interior Conversion in Garland, TX: What It Costs and How Long It Takes
A junior ADU and interior conversion in Garland typically runs $45,000 to $130,000 and takes 10 to 16 weeks from permit to final inspection. That range covers converting an existing interior space (a spare room, an attached garage bay, an oversized utility area) into a code-compliant junior accessory dwelling unit while upgrading the surrounding house at the same time. Most Garland projects we quote land between $70,000 and $95,000. Call (888) 426-8078 for a free on-site estimate, and we’ll give you a written line-item number before anyone touches a wall.
Key takeaways:
- Junior ADU & Interior Conversion in Garland: $45,000 – $130,000, 10 – 16 weeks
- The hidden cost driver in Garland’s older core is usually electrical service and foundation, not the finish work
- Permits and city inspections are required; we pull them and stand behind the inspection
- Live person answers the phone 24/7, and every project is covered by the 730-Day Done Right Promise
How we run a junior ADU & interior conversion, stage by stage

Here’s the real sequence, with what you’re deciding at each point. No surprises in the middle.
Stage 1: Site and feasibility walk (week 1)
We spend two to three hours in your Garland home measuring the candidate space, checking the panel, and looking at how the existing floor sits against the slab. At this stage you decide which room becomes the junior ADU. We tell you honestly if the electrical service or foundation makes a particular room a poor fit. This is where most surprises get caught, not later.
Stage 2: Drawings and permitting (weeks 2 – 5)
We produce the plan set and submit to the City of Garland. Garland runs its own permitting and inspections rather than deferring to Dallas County, so plan review typically runs three to five weeks depending on queue volume. You decide the layout of the kitchenette and the bathroom door swing here, because changing either after permitting restarts the clock. This is also when you finalize whether the junior ADU entry is a separate exterior door or a shared interior hall.
Stage 3: Demo and rough-in (weeks 6 – 8)
Framing adjustments, plumbing rough-in, electrical rough-in, and HVAC runs happen in this window. Rough inspections follow immediately. On Garland’s older ranch homes, this stage is when we frequently find the hidden cost: an undersized or fuse-era panel that has to be upgraded to support a junior ADU’s kitchenette and dedicated circuits. You decide appliance placement and any fixture relocations here, before drywall closes the walls.
Stage 4: Finishes and interior conversion (weeks 9 – 13)
Insulation, drywall, flooring, cabinetry, countertops, tile, and trim all go in. The “interior conversion” side of the job lives here: the surrounding house gets the wall repairs, paint patching, and door replacements that come with carving out a junior ADU. You decide material grade at the front of this stage, not the middle. We source through our vetted brand partners so the finish you pick is the finish you get.
Stage 5: Final inspection and walkthrough (weeks 14 – 16)
Final inspection, punch list, and the walkthrough where we hand you the paperwork and the warranty. You approve the punch list before we call it done. Our 730-Day Done Right Promise starts the day you sign off.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The options you’ll choose between on a junior ADU & interior conversion
These are the decisions that actually move the result. Every one of them has a trade-off, and we’ll give you the honest version of it.
- Kitchenette vs. full kitchen. A junior ADU typically allows a compact kitchenette (sink, two-burner cooktop, small fridge, microwave). A full kitchen with a standard range adds cost and triggers heavier electrical. The trade-off: kitchenettes keep the budget in the $45,000 – $75,000 end, but limit the unit to a single occupant or couple.
- Wet-wall addition vs. existing plumbing stack. Tying the junior ADU bathroom to an existing stack saves $4,000 – $9,000. Tying in a new bathroom away from the stack costs more but gives you a nicer layout. If plumbing relocation is on the table, this is where the number moves.
- Electrical service upgrade. If your Garland home still runs a 100-amp or fuse-era panel, upgrading to 200-amp adds cost but is often unavoidable. We don’t skip it, because a junior ADU on an undersized panel fails inspection.
- Impact-rated exterior door. Garland gets hail and high wind. On the exterior entry we install impact-rated doors from brands like Therma-Tru and ES Windows. The cost is a modest premium over builder-grade, and the difference shows up when a storm rolls through.
- Window glass choice. Impact-rated glazing from ECO Window Systems or Mr-Glass holds up against hail. Standard dual-pane costs less up front. If the junior ADU has exterior windows exposed to the west or north, impact-rated is worth the upgrade.
- Flooring. Luxury vinyl plank over a concrete slab handles Garland’s seasonal movement better than solid hardwood. Tile in the bathroom, LVP in the bedroom and kitchenette is the combo we recommend most often.
What Junior ADU & Interior Conversion costs in Garland, TX

Our Garland junior ADU & interior conversion projects run $45,000 – $130,000. Most land in the $70,000 – $95,000 middle. Here’s what moves the number:
| Factor | Low end | High end |
|---|---|---|
| Space already framed and finished | Existing room conversion | Garage bay with new framing and slab |
| Plumbing | Ties to existing stack | New wet wall, relocated drain |
| Electrical | Adequate panel, add subpanel | Full service upgrade from 100-amp |
| Foundation repair | No condition found | Slab stabilization on clay soil |
| Finish grade | Builder-grade cabinetry and LVP | Mid-grade cabinetry, tile, upgraded fixtures |
A written estimate from us includes: plan set, permit submittal and fees, demolition, rough framing, plumbing rough and final, electrical rough and final, HVAC, insulation, drywall, flooring, cabinetry, countertops, tile, trim, paint, final inspection coordination, and the 730-Day Done Right Promise. It does not include: appliance purchases you make yourself, landscaping restoration outside the unit’s footprint, or structural repairs discovered after demo that couldn’t be seen at bid. When those come up, we bring you a written change order before doing the work. The number you see is the number you pay, and 0% financing is available for 18 months with $1,000 off projects over $10,000.
See the difference
Before
After
Before
After
Before
AfterWhat Garland homes specifically do to this job
Garland is a post-war streetcar suburb that grew into a full city, and its building stock splits along a line of construction era. The older core (75040, 75041, 75042, near downtown and the original 1950s-60s subdivisions) is full of single-story brick ranches built on slab-on-clay with undersized panels and modest framing. Push east and north into the 1970s-90s and newer master-planned additions, and you’re walking into two-story brick-and-frame homes with 200-amp service and modern building code. The expertise here is knowing which decade of code, framing, and systems we’re walking into before we bid. That age split, layered over a city that runs its own permitting and inspections rather than handing off to Dallas County, is what makes a Garland junior ADU project its own animal.
North Texas Blackland Prairie clay expands and contracts dramatically between wet springs and hot dry summers. On the older ranches near the downtown core, that means we check slab grade and foundation before promising a junior ADU on a particular room, because a settled slab will pull a floated floor apart. Hail and high wind events are routine here, which is why we spec impact-rated doors and windows on any exterior wall of the new unit. And Garland’s own inspection schedule means the rough-in timing has to be planned around their availability, not ours. Our technicians have up to 12 years of experience working on both sides of that age split. We also cover nearby Garland neighborhoods and neighboring communities across the eastern Dallas County line.
Serving Garland, TX – Our Local Coverage Area
We serve Garland and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Junior ADU & Interior Conversion in Garland

Ten to sixteen weeks is typical, with permitting accounting for three to five of those weeks. Construction itself runs seven to eleven weeks depending on scope. Call (888) 426-8078 for a project-specific timeline after we walk the space.
Yes. Any junior ADU or interior conversion with a kitchenette or bathroom requires a permit and inspections from the City of Garland. We pull the permits and coordinate every inspection. You don’t chase the paperwork.
Often, yes. If the space already has an adjacent bathroom or the plumbing stack is within reach of a wet wall, we can usually avoid a major relocation. That keeps the job in the $45,000 – $75,000 range. If plumbing has to move, expect $10,000 – $25,000 more. Call (888) 426-8078 and we’ll tell you after a walkthrough which side you’re on.
$45,000 to $130,000, with most Garland projects landing between $70,000 and $95,000. The variables that push high are electrical service upgrades, foundation work on clay soil, plumbing relocation, and finish grade. Call (888) 426-8078 for an exact quote, estimates are free.
The 730-Day Done Right Promise covers our workmanship for two full years from final inspection. If something fails because of how it was built, we make it right. That’s one of the longest workmanship guarantees in residential construction, and it’s in writing.
Homeowners often pair a junior ADU with Kitchen Design & Layout in Garland for the main house at the same time, or a Small & Partial Kitchen Remodels in Garland on the adjacent kitchen. When the junior ADU ties into a wider addition, we coordinate the scope under Home Additions & ADU in Garland, and you can see the full picture on our Home Additions & ADU service page.
Get a written junior ADU & interior conversion estimate in Garland
Call (888) 426-8078 for a free on-site estimate. We’ll walk the space, check the panel and slab, and hand you a line-item quote with a realistic schedule inside a week. Live person answers 24/7. Numbers are upfront and don’t change mid-job. Every project backed in writing by the 730-Day Done Right Promise.
Written by the team at Groundwork Construction Co.