Garage Conversion ADU in Garland: What It Costs and What It Takes
A Garage Conversion ADU in Garland typically runs $45,000 – $130,000 and takes 3 to 5 months from permit to final inspection. The job turns an attached garage into a legal, permitted living unit: new framing and insulation where the old wall met the garage, a raised or finished floor over the existing slab, full electrical and plumbing for a kitchenette and bath, HVAC extended from the house or split off it, and a door swap where the overhead door used to be. Call (888) 426-8078 to schedule a free on-site estimate.
What the work actually looks like, stage by stage

Most Garland garage conversions follow the same order, and the order matters because inspections gate the schedule. Here’s how a job moves.
Stage 1: Site assessment and design (week 1 – 2)
We walk the garage and the house together: measure the slab, check for cracking and settlement, trace the existing electrical panel and HVAC, and look at where a bathroom drain can tie into the main. You decide the layout here – studio versus one-bedroom, kitchenette wall versus open, closet placement. This is also where the big question gets answered: does the panel have room, or does it need a service upgrade?
Stage 2: Permits and engineering (week 2 – 5)
Garland runs its own permitting and inspections rather than deferring to Dallas County, so the packet goes to the city and comes back with comments you should expect to address. Plans for a habitable unit need to show egress, smoke and CO detection, insulation values, and the bath vent. If the slab or an existing header needs an engineer’s letter, that adds a week or two. You sign off on the final plan set before demo starts.
Stage 3: Demo and rough-in (week 5 – 8)
The overhead door comes out and gets framed and sheathed. We demo interior finishes, run new electrical circuits, set the bath plumbing and vent stack, extend or split the HVAC, and frame any new partition walls. Rough inspections for framing, electrical, plumbing, and mechanical happen before anything gets closed up. This is the loudest, dustiest stretch – usually two to three weeks of it.
Stage 4: Insulation, drywall, and finishes (week 8 – 13)
Spray foam or batt insulation goes in the exterior walls and ceiling, then drywall, then texture and paint. Flooring, trim, doors, the kitchenette, and bath fixtures follow. You’ll pick finishes during stage 2 so nothing stalls here – tile, cabinet color, countertop, fixtures, and door style are all decisions you make early, not mid-job.
Stage 5: Final inspections and walkthrough (week 13 – 18)
Final electrical, plumbing, mechanical, and building inspections close the permit. We do a punch walkthrough with you, fix what’s on the list, and hand over the signed-off documentation. Most Garland conversions land inside that 3-to-5-month window. Add 4 to 6 weeks if a service upgrade or foundation work gets pulled in.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The choices that actually change the number
Two conversions of the same 400-square-foot garage can differ by $50,000 based on what you pick. These are the decisions worth thinking through before you sign.
- Full kitchen versus kitchenette. A sink, mini-fridge, and microwave niche keeps plumbing short and costs the least. A real range and full-size fridge need a dedicated circuit, more counter, and cabinet run – more money, more appeal to a renter or family member.
- Bathroom configuration. A walk-in shower saves floor space and framing versus a tub, and a rear-vent or macerating toilet can avoid tearing up slab for a drain line. Every foot you move the drain from the tie-in adds cost.
- Floor strategy. Building the floor up over the slab with a vapor barrier and sleepers handles minor slab dips and keeps ceiling height reasonable. Grinding and coating the slab is cheaper but leaves it cold and unforgiving.
- HVAC approach. Extending the house system is simplest if the equipment has capacity. A mini-split gives the unit its own control and its own utility meter path, which matters if you’ll rent it.
- Overhead door replacement. Swapping the garage door for a framed wall with a window and a Therma-Tru or similar entry door is the standard move. Keep in mind curb appeal – a flat panel where the door was reads cleaner from the street than a patch.
- Windows and glazing. The old garage wall may have none. Adding windows changes light and livability, and products like ES Windows or ECO Window Systems give you options at different price points.
What a Garage Conversion ADU costs in Garland, TX

Plan on $45,000 – $130,000 for a permitted conversion in Garland. Most single-bay conversions on a 1950s – 70s ranch land in the $60,000 – $90,000 range; a larger two-car conversion with a full kitchen, upgraded finishes, and a service upgrade pushes toward the top.
What moves the number:
- Size. A 240-square-foot single bay and a 480-square-foot double bay are different jobs. Square footage drives framing, drywall, flooring, and HVAC load.
- Electrical service. Older Garland homes often still carry a 100-amp panel, sometimes fuse-era. A service upgrade to 200 amps can add $2,500 – $6,000, and it’s the hidden cost on a job that looked simple from the curb.
- Slab and foundation condition. Blackland Prairie clay moves between wet springs and dry summers. Cracked or heaved slabs need leveling or a build-up, and that’s money.
- Plumbing distance. The farther the bath and kitchenette sit from the main drain tie-in, the more slab gets cut and the more it costs.
- Finish grade. Builder-grade tile and stock cabinets versus custom cabinetry and stone counters can swing $15,000 – $30,000 on its own.
A written line-item estimate covers design, permits, demo, framing, rough-in trades, insulation, drywall, finishes, fixtures, and final inspections. It typically does not cover a service upgrade if the panel turns out to be undersized, unexpected slab repair, or landscaping restoration – we flag those scopes up front rather than surprise you later. The number you see is the number you pay.
See the difference
Before
After
Before
After
Before
AfterWhy Garland’s building stock shapes this job
Garland is a post-war streetcar suburb that grew into a full city, and its housing splits sharply by era. The older core in 75040, 75041, and 75042 – around the original downtown and the 1950s – 60s subdivisions – is full of small single-story brick ranches with attached garages that were never built for habitable use. Out toward the newer ZIPs, the homes are 1970s – 90s subdivisions and later two-story brick-and-frame builds. A conversion bid depends entirely on which decade of code, framing, and systems we’re walking into.
The mid-century ranches are where the surprises live. The garage slab was often poured as a separate pour from the house and has had 60 years of clay movement underneath it. Electrical service is frequently still 100-amp or fuse-era. Insulation is minimal or absent. That combination is what turns a straightforward conversion into a $90,000 job rather than a $60,000 one, and it’s why we inspect the panel and slab before we quote. Hail and wind events are a routine part of life here too, so impact-rated materials on the new exterior wall are a sensible choice rather than an upsell. We cover all of Garland for this work, from the older core out to the newer subdivisions.
Serving Garland, TX – Our Local Coverage Area
We serve Garland and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently asked – Garage Conversion ADU in Garland

Most conversions take 3 to 5 months from signed contract to final inspection, with permitting and inspections eating 3 to 6 weeks of that. A service upgrade or slab work can add 4 to 6 weeks. Call (888) 426-8078 for a timeline specific to your garage.
Yes. Garland runs its own permitting and inspections, and a habitable unit needs building, electrical, plumbing, and mechanical permits with final sign-off before it can be legally occupied or rented. We pull the permits and manage every inspection as part of the job.
Sometimes, but rarely. A bathroom or kitchenette needs a drain and supply lines, which means cutting into the slab or finding a tie-in point. Egress, insulation, and the door swap are structural-adjacent by nature. If the existing header and slab check out, the scope stays lean; if not, we price the fix before demo.
Not from our end. We give you a written line-item estimate with fixed pricing, and the scope is locked before demo. If we open a wall and find something genuinely hidden like a failing slab or an undersized panel, we stop, show you, and get written approval before adding cost. No change orders out of nowhere.
Every conversion we build is covered by our 730-Day Done Right Promise – if it’s not done right, we make it right. That’s one of the longest workmanship guarantees in the residential construction space, and it applies to the whole job.
Get a free on-site estimate for your Garland conversion
Tell us about the garage and we’ll walk it with you, check the panel and slab, and put a written line-item number in your hands. Call (888) 426-8078 – a live person answers, day or night. We’ll talk through layout, timeline, financing (0% for 18 months), and the $1,000 off projects over $10,000. If the conversion is part of a full Home Additions & ADU in Garland plan, we scope both together so nothing gets rebuilt twice. Homeowners often pair the interior finish work with Cabinets & Countertops in Garland and Backsplash, Tile & Flooring in Garland. To see the wider range we handle, browse our Home Additions & ADU service.
Written by the team at Groundwork Construction Co.