New Detached ADU in Garland, TX: What the Build Actually Looks Like
A new detached ADU in Garland typically runs $45,000 to $130,000, takes four to seven months from survey to final inspection, and is a fully separate structure on its own foundation with its own power meter. If you’ve got a deep lot off a post-war street in 75040 or acreage out toward the eastern edge of Garland, the math often clears. Call (888) 426-8078 and we’ll walk your lot and give you a real number, not a ballpark over the phone.
How We Build a Detached ADU, Stage by Stage

Nothing about a detached structure rewards shortcuts. Each stage has to pass before the next one starts, and Garland runs its own inspections rather than handing them to the county, so the sequence is not optional.
Stage 1: Lot survey and site plan, roughly two to three weeks. We start by pulling the plat and confirming setbacks, easements, and utility locations. On Garland lots this is where we find out whether the alley access, drainage swale, or an existing sewer line can carry a second structure. You decide the footprint and where it sits. This is the cheapest time to make that call.
Stage 2: Permitting, four to eight weeks. We submit the site plan, architectural drawings, and engineering for the foundation. Garland’s building department wants a foundation design suited to Blackland Prairie clay, so a generic out-of-state plan will bounce. You sign off on the drawings and we handle the submittal. Building in an existing neighborhood can add homeowner association review on top of the city review.
Stage 3: Site prep and foundation, one to two weeks. We clear the pad, grade for drainage, and pour. On a lot that has an aging slab or a leftover shed, demolition gets folded in here. You’ll want to know beforehand whether heavy equipment can get past your fence line and where the access will run.
Stage 4: Framing, roof, and rough-in, four to six weeks. Standing walls, setting trusses, sheathing, then the roof. Then comes electrical, plumbing, and HVAC rough-in, followed by the rough framing and rough mechanical inspections. This is the point where any decision about interior layout needs to be final, because moving a wall after rough-in costs real money.
Stage 5: Insulation, drywall, finishes, final inspection, four to six weeks. Insulation, drywall, tape, texture, then cabinets, flooring, fixtures, and paint. Final inspection clears the certificate of occupancy. You walk it with us and we correct anything on the punch list before we’re done.
The whole sequence runs four to seven months on a straightforward lot, and longer if the site needs grading work or utility relocation. We keep the schedule written down so you know what’s supposed to happen each week.
Styles & brands we work with
- Kitchen remodeling
- Bathroom remodeling
- Home additions & ADU
- Roofing
- Windows & doors
- Driveway & pavers
- Fence
The Options You’ll Choose Between
Most of the decisions that shape both the price and how the finished unit lives come down to a handful of choices. Here’s the honest trade-off on each.
- Footprint and layout: A one-bedroom unit at 500 to 650 square feet suits a single renter or an aging parent. A two-bedroom at 750 to 900 square feet opens the door to a wider tenant pool but adds cost across foundation, framing, and mechanical. Open plans feel bigger but give up privacy for a live-in relative.
- Foundation system: A post-tension slab is the standard and most cost-effective choice on North Texas clay. A pier-and-beam approach costs more up front and is worth discussing if the surrounding soil drains poorly or the site is graded unevenly.
- Roofing: Architectural shingles from GAF or CertainTeed are the practical default. Impact-resistant shingles cost more but matter in Garland, where hail is a routine event, and some insurers discount for them.
- Windows and doors: ES Windows and Therma-Tru are the two names we reach for most on a detached unit. Low-E glass keeps the summer load down. Sliding doors save floor space; a hinged entry with a proper threshold holds up better over years of foot traffic.
- Kitchen and bath grade: A basic appliance package with laminate counters gets the unit rentable. Quartz or solid surface counters and mid-tier appliances hold up better and pull a better tenant. There’s a sweet spot and we’ll tell you where it sits for your rental goals.
- Utilities and metering: A separate electrical meter lets you bill a tenant directly. Tying into the main house service is cheaper up front and messier long term. The decision has to be made before the electrical permit goes in.
What New Detached ADU Costs in Garland, TX

Detached ADU construction in Garland runs $45,000 to $130,000. The range is wide because the variables below swing hard on this job. A straightforward 500 square foot unit on a flat, easy lot with a tie-in to the existing service will sit near the bottom. A larger unit with a separate meter, a pier foundation, and upgraded finishes pushes toward the top.
The variables that move the number:
- Size: Square footage drives foundation, framing, insulation, and finishes. Each additional 100 square feet adds roughly $8,000 to $15,000 depending on finish grade.
- Site condition: An uneven lot, root-heavy ground, or a drainage problem adds grading and dirt work that a clean pad doesn’t need.
- Utility runs: Distance from the main house to the ADU pad is the hidden driver. Long trench runs for sewer, water, and power add cost fast, and a new meter and service panel add on top.
- Finish grade: Flooring, cabinets, countertops, and fixtures are where you choose between a workmanlike unit and a premium one. Cabinetry alone can swing the number by thousands.
- Permit scope: A unit with a full kitchen and laundry has more inspection steps than a simple guest suite. The drawings, engineering, and review cost more too.
A written estimate from us is line-item: foundation, framing, mechanical rough-in, finishes, permits, and site work each on their own line. What it doesn’t include is landscaping, fencing beyond the ADU footprint, and any appliance package above the standard tier unless we’ve priced it in. Upfront pricing, no surprises means the number on the page is the number you pay, and if something genuinely unseen surfaces we stop and quote it before we touch it.
See the difference
Before
After
Before
After
Before
AfterWhat Garland Homes Specifically Do to This Job
Garland’s building stock splits along a line of construction era, and that split changes how we bid an ADU. Near the old downtown core and the original 1950s-60s subdivisions in 75040 and 75041, you’re working around small single-story brick ranches on shallow lots, where the alley is narrow and the original electrical service is often 100-amp or fuse-era. Running power out to a new structure from a panel that’s already full is the hidden cost driver on a job that looked simple from the curb. Foundation work on those lots means dealing with original slab-on-clay conditions that have settled over decades.
Out toward the northern and eastern ZIPs, the picture changes: 1970s-80s and newer subdivisions with larger lots and room for a real detached structure. The soils are the same expansive Blackland Prairie clay, so we design the foundation for movement either way, but the access and the electrical service usually give us more to work with.
Garland runs its own permitting and inspections, which means plan review is local and specific rather than routed elsewhere, and a stamped foundation design for our soil is expected. Hail and high wind make the roof and cladding decisions matter here more than they would in a milder climate, which is why we steer toward impact-resistant shingles and wind-rated assemblies. If your ADU is part of a full Home Additions & ADU in Garland plan that also touches the main house, we sequence both under one set of drawings so the inspections line up.
Serving Garland, TX – Our Local Coverage Area
We serve Garland and nearby communities. Use the map below to see the area we cover. If you’re nearby, we can almost certainly help.
Frequently Asked – New Detached ADU in Garland

Four to seven months from survey to certificate of occupancy on a straightforward lot. Permitting alone runs four to eight weeks because Garland reviews locally, and construction runs three to four months after that. Call (888) 426-8078 for a schedule based on your actual lot.
Yes. A detached dwelling unit needs building, electrical, plumbing, and mechanical permits plus a certificate of occupancy, and Garland’s own department issues them. There’s no pathway around it, and we pull the permits and pass the inspections as part of the job. Call (888) 426-8078 and we’ll outline the review steps for your address.
Often yes. We can tie the new unit into the existing electrical service and run shared utilities if the panel has capacity, which is cheaper than a new meter. The determining factor is whether the main service can carry the added load without an upgrade, and whether the trench run is short. We check that during the site survey and tell you which way makes sense.
$45,000 to $130,000 depending on size, site conditions, utility runs, and finishes. The written estimate is fixed for the scope described. If we open the ground and find something genuinely unexpected, we stop and quote the change in writing before doing it. Call (888) 426-8078 for an exact number on your lot.
Every detached ADU we build is covered by our 730-Day Done Right Promise: if it isn’t done right, we make it right. That’s one of the longest workmanship guarantees in residential construction. Our technicians have up to 12 years of experience and they’re background-checked and arrive in uniform. Call (888) 426-8078 with questions about coverage.
Get a Real Number on Your Garland Lot
We’ll come out to your property, walk the lot, check the setbacks, look at your existing electrical service, and tell you honestly what a new detached ADU will cost here. No sales pitch, no vague ranges: a line-item estimate for your address. Call (888) 426-8078 to schedule your free estimate. If you’re also planning interior work, ask about our Kitchen Design & Layout in Garland service while we’re out there, and homeowners often pair the ADU build with Backsplash, Tile & Flooring in Garland inside the main house. We cover Garland, and if you want the wider picture on additions, see our Home Additions & ADU service.